Socialville-Fosters Improvements/Roundabout

PROJECT SUMMARY
Location: Deerfield Twp
Cost:
Status: Completed
Start Date:
End Date:
Project Participants:
Scope: Socialville-Fosters Road was widened from two to five lanes from Innovation Way to Columbia Road, and the bridge over I-71 was replaced.
As part of this project, a new double-lane roundabout was constructed at Socialville-Fosters Road and Innovation Way, including intersection and signal improvements at Columbia Road. The roundabout is now a four-legged roundabout with the southern leg being built in anticipation of the extension of Innovation Way south from Socialville-Fosters Road to Duke Boulevard (construction to occur in 2017).
In addition, a new southbound right turn lane has been added at the intersection of Socialville-Fosters Road and Columbia Road.
A five-foot wide pedestrian walkway on the north side of the road between Innovation Way and Columbia Road has been built.